Completion of project “Upgrade capacity of 220kV Nam Dinh substation

Thứ năm, 🐼21/7/2016 | 00:00 GMT+7
​​At 07h45 on June 10th 2016, in 220kV Nam Dinh substation, Power Transmission Company No. 1 combined with the relevant units organized commissioning and putting into operation of the 220kV-250MVA AT2 transformer completing the project “upgrade capacity of 220kV Nam Dinh substation from 125+250MVA to 2x250MVA.

MBA AT2 220kV-250MVA_170616.jpg
The 220kV-250MVA AT2 transformer at 220 kV Nam Dinh substation

The energizing and putting into operation of the 220kV-250MVA AT2 transformer are not only to increase capacity for the 220kV Nam Dinh substation, meeting demand o🐼n power load growth and socio-economic development of Nam Dinh province and surrounding areas, but also ensure a secure, stable operation of power transmission system for serving the socio-economic development, national defense in the region.

The project “upgrade capacity of 220kV Nam Dinh substation from 125+250MVA to 2x250MVA” has a total cost of over VND 85 billion invested by National Power Transmission Corporation (EVNNPT); PTC1 is responsible for managing the project, Power Engineering Consultation Company 3 (PECC3) is responsible for project design; Power Construction Company 1 – Dai Mo (PCC1 –Dai Mo) is responsible for construction, the units under PTC1 are responsible for installation of primary, secondary equipment, testing, including Pow💞er Testing Division, Power Equipment Maintenance Division, Ninh Binh Power Transmission and Mechanical Transportation Division.

The main scope of project: to replace the existing 220kV-125MVA AT2 transformer by a 220kV-250MVA transformer; to supplement, replace and install the relevant equipment for the new transf♏ormer./.

Operations

Operations

Investment

Investment

International relations

International relations

Event Calendar

Event Calendar

{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|