AT2 220kV-250MVA transformer at 220kV Nam Dinh
substation
The energization and putting into
operation of AT2 220kV-250MVA transformer MBA at 220kV Nam Dinh substation not
only provides electricity directly to Nam Dinh, Thai Binh 🌠and Ha Nam provinces
but also plays an important role in ensur൩ing the national power transmission
network safe, stable, contributing to the social-economic development, security
and defense of the Southern Red River delta.
The project "Increasing the
capacity of 220kV Nam Dinh substation from (125 + 250) MVA up to 2x250MVA"
has the total investment of over 84 billion with the National Power
Transmission (EVNNPT) as the investor; Power Engineering Consulting joint stock
company 3 (EVNPECC3) as designing consultant, units of Power Transmission company
1 (PTC1); Equipment repair workshop, Ninh Binh power transmission company, Experiment
workshop responsible for the ไimplementation.
The project has a total construction
and investment: replacing the existing 220kV- 125MVA transformer with a
220kV-250MVA transformer; replacing and installing additional equipment to suit
the new t𒊎ransformer.
The construction was started on
29/05/2015 i𒐪nside Nam Dinh 220kV substation and located in My Phuc commune, My
Loc district, Nam Dꦫinh province./.