The project is invested by National Power
Transmission Corporation (EVNNPT),
CPMB is on behalf of EVNNPT to manage
the project, Power Engineering Consulting C🌊ompany 3 (PECC3) is responsible for
project design, Power Construction Company No. 2 (PCC2) is responsible for
implementation, Power Transmission Company No. 3 (PTC3) takes over the pro♛ject
management and operation.
Despite of many difficulties in compensation
and ground clearance, with high determination, CPMB in combination with
implementing contractor and relevant units have gathered human resources,
equipment, combined with local authorities to push up project impleme🔴ntation
even in holidays 30th April and 1st May so th𝓀at project was energized in time.
The 220kV pow💟er transmission project connecting
Dak Nong Aluminium Electrolytic Plant is of special preferential investment apꦉproved
by the Government at Decision No. 822/QĐ-TTg dated 30th May 2014.
The project was started on 27th May 2016, with
total investment cost of VND 160 billion, of which VND 135 billion is from
commercial credit provided by Indovina Bank – Hoi An branch and EVNNPT’s equity.
The scope of project i🗹s to construct 03 new
220kV double circuit transmission line routes, of total length of about 12.74
km. The transmission line is constructed in Nhan Co commune, DakRlap district,
Dak Nong province./.