Energizing and commissioning the 220kV Ben Tre – Mo Cay transmission line project

 Thứ ba, 23/6/2015 |☂ 00:00 GMT+7 𒀰
​​At 12h40, on June 11th 2015, at the 220kV Ben Tre substation, Southern Power Projects Management Board (SPMB) combined with consulting, construction, management companies organized energizing and commissioning the 220kV Ben Be – Mo Cay transmission line project and 2 feeders at the 220kV Ben Tre substation. The project has been completed 2 months ahead schedules. This project has been registered by SPMB as a typical one to be honour of EVNNPT’s session II Party Congress, term 2015-2020.
DZ 220kV Ben Tre - Mo Cay_11-6-2015_1.jpg 
The 220kV Ben Tre – Mo Cay transmission line: Conductor stringing is under implementation

The scope of project is to build a new double-circuit 220kV transmission line, of a length of 2x19.7km (from the 220kV Ben Tre substation to 220kV Mo Cay substation) and expand 2 feeders at 220k🌜V Ben Tre substation. The project runs through area of Ben Tre city and districts🌄 of Mo Cay Nam, Mo cay Bac of Ben Tre province.

The project has a total cost of over VND 482 billion, invested by EVNNPT; SPMB✨ is on behalf of EVNNPT to manage the project; Project design  is done by Power Engineering Consultation Company No. 3 (PECC3), Project implementation is done by Power Consulting Company No. 1 (PCC1). After the project is completed, management and operation of project will be done by Power Transmission Company No.ℱ 4 (PTC4) .

The project construction is to provide a stable power supply to the national defense, socio-economic development of Ben Tre province and surrounding areas. The 220kV Ben Tre – Mo Cay, together with 500kV Duyen Hai substation, 500kV Duyen Hai - My Tho transmission line, 220kV Duyen Hai - Mo Cay transmission line (expected to be completed in 2015) will evacuate entire capacity of Duyen Hai Power Centre into tꦚhe national power system, creating a stable linkage between Duyen Hai Power Centre and the 500kV/220kV transmission lines, which ensures a stable power supply to the South-Western area.

The effor෴ts made by SPMB staff who spent weekends to settle the difficulties, outstanding in compensation, site clearance for 687 a🍌ffected households, as  well as the fact that project completed 2 months before schedule have shown high efforts, determination by entire SPMB staff in emulation movement to complete project to be honour of EVNNPT’s session 2 Party Congress, term 2015 – 2020./.

Other News

Operations

Operations

Investment

Investment

International relations

International relations

Event Calendar

Event Calendar

{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|{tk88 bet}|